Air Handling Plant Replacement

A recently completed main Air Handling Plant replacement project in the Greenford area was carried out by the engineering team at Planned Technical Services. The Air Handling Unit removal and location was particularly challenging due to the limited space and the internal location of the plant. This was successfully completed by utilising a sectional delivery of the unit, located into position with a crane specialist and then assembled by hand in situ. The plant and associated ductwork was commissioned and handed over to the client in a very short period following the delivery from the manufacturers.

PTS were tasked to replace existing AHU with a heat recovery AHU, system as craned up in small sections and assembled on site. Modifications to ductwork etc

This is the after photos of the assembled equipment.